Structural Roof Truss Placement on Tight Residential Infill
Contract Lift & Long Reach Hiab
The Challenge
A new-build coastal property required multiple pre-fabricated timber roof trusses lifted over a 2-storey existing residence into a narrow rear building plot. Overhead residential telephone lines and zero road closure availability on a busy residential street prevented static mobile crane setup.
The Solution
We deployed our 32t 8x2 long-reach unit equipped with multi-stage hydraulic fly-jib extensions. Our Appointed Person produced full BS7121 lift calculations, utilising dual-padded slings and stabilizing outriggers on the tight street footprint without blocking emergency access.
The Outcome
All truss bundles were lifted, rotated, and placed directly onto wall plates in under 4 hours, allowing the carpentry contractors to secure the roof structure ahead of impending coastal weather.